Roncelli, Inc. was the Construction Manager for this 3,200 square foot suite build out on the second floor of Beaumont Royal Oak Hospital’s Neuroscience Center. Construction was completed within a 12 week schedule.
Construction materials into the suite and debris out of the work areas was scheduled during non-operational hours of the building. Work requiring noise or vibrations was also handled during building shut downs.
The scope of work included new partitions, new wall, floor and ceiling finishes and complete, new mechanical and electrical systems throughout the space. The Neurology & Educational Center components consisted of a Speech, Vestibular and Vision Therapy, Gym area, Classroom, Workroom, new restrooms and a Reception and Waiting Lounge.